Thru hull and seacock installation

I recently contracted someone to do various work on my boat and among these things was the removal of and installation of all new thru hulls and seacocks, of which there are 9 total. I had two of them permanently closed up but the others were put in with just the threaded thru hull and backing nut.

This contractor, even with 20 years of experience, was dumbfounded at the suggestion that he use flanged seacocks with backing plates instead of simply screwing a valve onto a thru hull with only the backing nut. He is a motor yacht type, not an offshore sailor. The thru hulls were installed professionally, he used 5200, and they are strong, clean, and look good but they are still only held in with the backing nut that's included with the thru hull. He also prepped, dried, and epoxied the existing holes in the hull so that they are strong as well.

Here is my question: Since this person no longer works for me, and I am going to add backing plates and flanges to all of these thru hulls, do I need to completely remove them all and start from scratch or can I (would you) gingerly screw on and seal a flange adapter to the existing thru hull? They have been in for a number of weeks now and the 5200 is completely cured.

I will remove them and start over if I have to. I'll be finishing this project myself. But I am concerned about breaking loose the thru hull seal as they are when I screw down a flange and seacock. Are the thru hulls strong enough to withstand the torque of adding a flange and valve? Would you have someone outside holding the mushroom head with a spud wrench while making these additions?

Currently I am leaning towards just adding the flanges and valves to the existing new thru hulls. Any advice on this would be hugely appreciated. I really don't want to break all these things out and start over.

We sail extensively and cruise full time with children. Although we don't currently cross oceans we do make hops from the Bahamas to the USVI.

Thanks!
luhtag is offline  
Sponsored Links
Advertisement
 
post #2 of 12 Old 02-20-2015
Senior Member
 
Dave_E's Avatar
 
Join Date: Aug 2013
Location: Everett, WA
Posts: 712
Thanks: 42
Thanked 24 Times in 24 Posts
Rep Power: 7
 
Re: Thru hull and seacock installation

5200 is STRONG stuff! Getting the inside nut to break loose will be your biggest chore depending on what kind of room you have for your wrenches. Once you do get the 5200 to break loose, everything will probably be loose and you'll be starting all over. You will more than likely need an outside helper with a special tool to "try" and hold things once you get them loose. Don't envy your task.

Dave

Allmand Sail 31 #15 "Traveler"
GOD, Family, career
Dave_E is offline  
post #3 of 12 Old 02-20-2015
Senior Member
 
Join Date: Feb 2011
Location: San Francisco Bay area
Posts: 3,180
Thanks: 9
Thanked 90 Times in 89 Posts
Rep Power: 9
 
Re: Thru hull and seacock installation

Quote:
Originally Posted by luhtag View Post
I recently contracted someone to do various work on my boat and among these things was the removal of and installation of all new thru hulls and seacocks, of which there are 9 total. I had two of them permanently closed up but the others were put in with just the threaded thru hull and backing nut.

This contractor, even with 20 years of experience, was dumbfounded at the suggestion that he use flanged seacocks with backing plates instead of simply screwing a valve onto a thru hull with only the backing nut. He is a motor yacht type, not an offshore sailor. The thru hulls were installed professionally, he used 5200, and they are strong, clean, and look good but they are still only held in with the backing nut that's included with the thru hull. He also prepped, dried, and epoxied the existing holes in the hull so that they are strong as well.

Here is my question: Since this person no longer works for me, and I am going to add backing plates and flanges to all of these thru hulls, do I need to completely remove them all and start from scratch or can I (would you) gingerly screw on and seal a flange adapter to the existing thru hull? They have been in for a number of weeks now and the 5200 is completely cured.

I will remove them and start over if I have to. I'll be finishing this project myself. But I am concerned about breaking loose the thru hull seal as they are when I screw down a flange and seacock. Are the thru hulls strong enough to withstand the torque of adding a flange and valve? Would you have someone outside holding the mushroom head with a spud wrench while making these additions?

Currently I am leaning towards just adding the flanges and valves to the existing new thru hulls. Any advice on this would be hugely appreciated. I really don't want to break all these things out and start over.

We sail extensively and cruise full time with children. Although we don't currently cross oceans we do make hops from the Bahamas to the USVI.

Thanks!
I am trying to think of a way to save you lots of work. All I can come up with is this :

Make an FR4 backing plate with a hole in it, that will fit over your through-hull. It will need a recess in it for the nut, as that is already stuck on with 5200. Place a second nut over the backing plate, put plenty of 5200 between the plate and the hull, and tighten down. You now have the load spread over a backing plate, without removing the through-hull.

Bristol 31.1, San Francisco Bay
MarkSF is offline  
 
post #4 of 12 Old 02-21-2015
Senior Member
 
mitiempo's Avatar
 
Join Date: Sep 2008
Location: Victoria B.C. Canada
Posts: 7,853
Thanks: 0
Thanked 113 Times in 104 Posts
Rep Power: 12
   
Re: Thru hull and seacock installation

You will have to remove the through hulls because the threaded section will have to be cut to the proper length so it doesn't bottom out in the flange. This link shows the entire installation.

Replacing Thru-Hulls and Seacocks Photo Gallery by Compass Marine How To at pbase.com

Send this link to your contractor:

Seacock & Thru-Hull Primer/Pre Information Photo Gallery by Compass Marine How To at pbase.com

Brian
Living aboard in Victoria Harbour
mitiempo is offline  
post #5 of 12 Old 02-21-2015
Senior Member
 
Morild's Avatar
 
Join Date: Mar 2013
Location: Aabenraa, Denmark
Posts: 166
Thanks: 3
Thanked 4 Times in 4 Posts
Rep Power: 7
 
Re: Thru hull and seacock installation

Where are they located?
Evaluate each location and find out if anything heavy can actually fall onto it while sailing. If not, I would not loose a seconds sleep over how they have been fitted already.
Morild is online now  
post #6 of 12 Old 02-21-2015
Senior Member
 
sailvayu's Avatar
 
Join Date: Feb 2013
Location: Ft Myers, FL, for now
Posts: 220
Thanks: 1
Thanked 18 Times in 16 Posts
Rep Power: 7
 
Re: Thru hull and seacock installation

What you have is what I call a ball valve on a thru hull. Not a proper seacock. It works but like you say is not the best solution. I have done a video series on replacing the valave on a lagoon 38 that may be of some help. This is a link to the first one
Not sure what type of boat you have or how you plan to use it. The one example of why a proper seacock should be used is a boat I was asked to look at that had stray current corrosion. The heads of the thru hulls were literary eaten off over a period of a week. The only thing left keeping the water out was the flanged seacock. If this boat had, had ball valves on thru hulls it would have sunk.

Capt. Wayne Canning, AMS

To view links or images in signatures your post count must be 10 or greater. You currently have 0 posts.


To view links or images in signatures your post count must be 10 or greater. You currently have 0 posts.
sailvayu is offline  
The Following User Says Thank You to sailvayu For This Useful Post:
luhtag (02-22-2015)
post #7 of 12 Old 02-22-2015 Thread Starter
Member
 
Join Date: Mar 2003
Posts: 31
Thanks: 1
Thanked 3 Times in 2 Posts
Rep Power: 0
 
Re: Thru hull and seacock installation

Quote:
Originally Posted by MarkSF View Post
I am trying to think of a way to save you lots of work. All I can come up with is this :

Make an FR4 backing plate with a hole in it, that will fit over your through-hull. It will need a recess in it for the nut, as that is already stuck on with 5200. Place a second nut over the backing plate, put plenty of 5200 between the plate and the hull, and tighten down. You now have the load spread over a backing plate, without removing the through-hull.
Yea I'm leaning toward this option.

Currently no valves are on the thru hulls. Just the mushroom head is installed. I have backing plates already made for all of them. I think what I'll do is countersink a hole for the thru hull nut, bolt the seacock flange adapter to the backing plate with countersunk bronze bolts epoxied in from the underside, then screw that on to the existing thru hull. I don't have to dog it down, and like the guy above said, 5200 is strong stuff. I doubt there'd be enough force in this to even come close to stressing the thru hull seal. Also the backing plate would be 5200'd in place on top of the thru hull. In addition I would use fiberglass tape and epoxy over the top of the backing plate to make it a permanent part of the hull. Once that is cured, I can just screw down the bronze ball valve snug to the adapter flange.

These seacocks are all over the boat. They are well protected so nothing would be hitting them. But still, I'd like them as strong as possible. The boat is a 1980 Gulfstar 50, so the hull is old school and pretty thick. No core in it. And like I said, the new thru hulls were done well even though they weren't done to the standard of the Compass Marine guy, whom I tend to trust implicitly. They would be fine without the flanged seacocks but I prefer things to be bullet proof. I think at this point, removing the thru hulls would just damage the hull and create more unnecessary work.
luhtag is offline  
post #8 of 12 Old 02-22-2015 Thread Starter
Member
 
Join Date: Mar 2003
Posts: 31
Thanks: 1
Thanked 3 Times in 2 Posts
Rep Power: 0
 
Re: Thru hull and seacock installation

Quote:
Originally Posted by sailvayu View Post
What you have is what I call a ball valve on a thru hull. Not a proper seacock. It works but like you say is not the best solution. I have done a video series on replacing the valave on a lagoon 38 that may be of some help. This is a link to the first one http://youtu.be/a9ZBrBWnNAs
Not sure what type of boat you have or how you plan to use it. The one example of why a proper seacock should be used is a boat I was asked to look at that had stray current corrosion. The heads of the thru hulls were literary eaten off over a period of a week. The only thing left keeping the water out was the flanged seacock. If this boat had, had ball valves on thru hulls it would have sunk.
I've watched your video many times and it's a great resource for everyone.

The mistake I made was trusting a contractor. I ASSumed that everyone understood new thru hulls and seacocks needed bronze flanges and the like but this guy was a world away from that, even after I specified. Damage done. All of his other work was top notch though so I relaxed in my micro management. Lesson learned, again.
luhtag is offline  
post #9 of 12 Old 02-22-2015
Senior Member
 
mitiempo's Avatar
 
Join Date: Sep 2008
Location: Victoria B.C. Canada
Posts: 7,853
Thanks: 0
Thanked 113 Times in 104 Posts
Rep Power: 12
   
Re: Thru hull and seacock installation

Quote:
Originally Posted by luhtag View Post
Yea I'm leaning toward this option.

I think what I'll do is countersink a hole for the thru hull nut, bolt the seacock flange adapter to the backing plate with countersunk bronze bolts epoxied in from the underside.....
There is no reason for the through hull nut. It adds nothing to the installation. The flange adaptor is the nut.

Markwesti likes this.

Brian
Living aboard in Victoria Harbour
mitiempo is offline  
post #10 of 12 Old 02-22-2015
Senior Member
 
Join Date: Feb 2011
Location: San Francisco Bay area
Posts: 3,180
Thanks: 9
Thanked 90 Times in 89 Posts
Rep Power: 9
 
Re: Thru hull and seacock installation

Yes, but the nut is now stuck in place with 5200.

Bristol 31.1, San Francisco Bay
MarkSF is offline  
Reply

Quick Reply
Message:
Options

By choosing to post the reply above you agree to the rules you agreed to when joining Sailnet.
Click Here to view those rules.

Register Now



In order to be able to post messages on the SailNet Community forums, you must first register.
Please enter your desired user name, your email address and other required details in the form below.
Please note: After entering 3 characters a list of Usernames already in use will appear and the list will disappear once a valid Username is entered.


User Name:
Password
Please enter a password for your user account. Note that passwords are case-sensitive.

Password:


Confirm Password:
Email Address
Please enter a valid email address for yourself.

Email Address:
OR

Log-in











Currently Active Users Viewing This Thread: 1 (0 members and 1 guests)
 
Thread Tools
Show Printable Version Show Printable Version
Email this Page Email this Page



Similar Threads
Thread Thread Starter Forum Replies Last Post
need to do seacock and through hull the_abuse Gear & Maintenance 14 05-07-2015 08:36 PM
Seacock installation/backing plates novic Gear & Maintenance 13 01-21-2015 09:42 PM
Thru-Hull and Seacock DaveOrchin Gear & Maintenance 1 11-16-2008 03:10 PM
Flanged seacock installation on the curve of the hull saurav16 Gear & Maintenance 6 06-22-2008 02:30 PM
Assemble thru-hull & seacock...how? flyhop Gear & Maintenance 10 04-09-2008 04:53 PM

Posting Rules  
You may post new threads
You may post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is On
Trackbacks are On
Pingbacks are On
Refbacks are On

 
For the best viewing experience please update your browser to Google Chrome